LPIC - EPC 3 Project Package III Building Works

Liwa Plastic Industries Complex (LPIC) EPC 3 NGL Extraction Project in Fahud is a natural gas extraction plant, and one part of six core components within the LPIC Steam Cracker project.

Our scope of work comprised the construction of 9 buildings including 3 substations, 2 satellite instrument handling buildings, main administration building, as well as warehouse and maintenance workshops and auxiliary buildings having a floor area of approximately 17,000 m2. The scope also included the J&I fit out and all MEP and fire protection.

DOHIproject-50
DOHI-project-27

Key Facts

  • Client: GS Engineering
  • Duration: 24 Months
  • Location: Fahud, Sultanate of Oman
  • Completion Date: March 2019