![](/wp-content/uploads/2018/04/ohi-icon-15.png)
Crowne Plaza
For the first time since its opening in 1975, the hotel closed its doors for 14 weeks to enable a fast and dynamic renovation by Douglas OHI.
Gulf Hotels wanted a contractor with in-house capabilities to deliver the refurbishment of their flagship hotel in Muscat.
The scope of works included the rebuilding of the entire pool area - new state of the art 2 level infinity pool with a cliff edge bar, an extension of the three-existing restaurants and a new café.
The main all-day dining restaurant was also redesigned and extended, along with a new reception area. This was supplemented by a new contemporary designed façade of the building, including external cladding, windows, doors and external wall finishes.
![Hotel Facade 2-a](https://www.douglasohi.com/wp-content/uploads/2019/10/Hotel-Facade-2-a.jpg)
![Infinity Pool -a](https://www.douglasohi.com/wp-content/uploads/2019/10/Infinity-Pool-a.jpg)
![IMG_7861-a](https://www.douglasohi.com/wp-content/uploads/2019/10/IMG_7861-a.jpg)
![IMG_7931-a](https://www.douglasohi.com/wp-content/uploads/2019/10/IMG_7931-a.jpg)
![](/wp-content/uploads/2018/04/ohi-icon-16.png)
Key Facts
- Being a fast track project meant that Douglas OHI had to be ready to mobilise ahead of schedule.
- Staff from across the whole business were invested to provide their expertise.
- Our dedicated team of staff worked two shifts over 24 hours for the duration of the project.
- 800,000+ Hours Accident Free
- 325 Site Inductions
- 5,145m2 Tiling
- 5,500m2 External Façade Refurbishment